Planning to Build After Dashain? A Post-Monsoon Pre-Construction Checklist

Reviewed by Anup Dhungana, Civil Engineer (NEC Reg. No. 11453 A), 2 October 2026

A phase-by-phase plan for Kathmandu homeowners: land checks, soil test, design, eBPS naksha pass and contractor selection, timed to the dry season.

If you want a crew on site by Mangsir, the time to start is now, not after tika. This year the monsoon dragged on, with heavy rain across Nepal from 24 to 28 September, and many families who planned to break ground in Ashwin are now looking at a post-Dashain start.

Most guides online stop at a cost-per-square-foot table. This one gives you the order in which things must happen, because the sequence decides whether your foundation goes in during dry Poush weather or during the first storms of Jestha.

Why sequencing matters more than speed

Every house built in the Kathmandu Valley has one hard deadline: the next monsoon. The Department of Hydrology and Meteorology (DHM) treats 2 October as the normal withdrawal date of the monsoon, and in 2026 the monsoon entered Nepal on 19 June, a few days later than average. Late exits and late entries are now common.

Work backwards from that window:

The one item you cannot speed up is the building permit (naksha pass). Recent guides report that Kathmandu Metropolitan City (KMC) takes roughly 30-45 days for the first-stage permit, including a 15-day public notice to neighbours. KMC's eBPS portal confirms that permits are issued in three stages but does not publish an official processing time, so treat 30-45 days as typical, not guaranteed.

Dashain 2083 runs from Ghatasthapana on 11 October to Kojagrat Purnima on 25 October, with Vijaya Dashami on 21 October. Government offices close for the main holidays, which is exactly why paperwork needs to start before then.

Phase 0 (now to Ghatasthapana): land and paperwork

Before an architect draws a single line, make sure the land itself is ready.

For more on land paperwork, see our guide to buying land in Nepal and land measurement in Nepal.

Phase 1 (Dashain, 11–25 October): decisions only you can make

Offices are closed, but the family is together. Use that time to agree on:

For NRN families, this is also the moment to decide who in Nepal will hold power of attorney (aakhtiyari) to sign documents on your behalf.

Phase 2 (Kartik): soil test and design

Soil test

Nepal's 2015 building bylaws made soil testing mandatory for private commercial houses and houses taller than five storeys. On filled land, slopes or riverside terraces, do it regardless of height. The soil test decides the foundation, and the foundation is the one part of your house you can never redo.

Architectural and structural design

KMC accepts drawings only from designers registered with the Nepal Engineering Council (NEC); the eBPS portal publishes a designer list. Simple houses may use standard designs, but you need full engineer-designed structural drawings if any of these apply:

Which seismic code?

Many guides still refer to NBC 105:2020, but KMC's eBPS portal now also lists the new NBC 105:2025 seismic design standard. Ask your structural engineer to confirm in writing which edition the design follows.

Design fees

Design fees are negotiated, not regulated. Industry estimates put them at roughly 2–5% of construction cost, or around Rs 50,000–2,00,000 for a typical family house.

Phase 3 (Kartik–Mangsir): eBPS and the three permit stages

StageWhat happensOwner's action
SubmissionDesigner uploads drawings and documents on eBPSSupply lalpurja, citizenship, tiro receipt, kitta naksa
Technical checkMetro checks bylaws and code complianceAnswer queries quickly
Ward inspection and 15-day noticeNeighbours can raise objectionsTalk to neighbours early
Fee paymentAround Rs 25 per sq ft of built-up area (residential, reported)About Rs 50,000 for 2,000 sq ft
Stage ITemporary permit up to plinth (DPC) levelNo superstructure yet
Stage IIPlinth inspection, then permanent permitBuild the plinth exactly to drawings
Stage IIICompletion certificateNeeded to sell, mortgage or transfer

You can follow your file on the eBPS "Application Track" page. For background on the process, see our earlier post on the building approval process.

Phase 4 (in parallel): BOQ, tender and contract

While the permit is in process, prepare the contract. Do not wait for approval to start this.

1. Prepare a Bill of Quantities (BOQ) from the structural drawings.

2. Ask at least three contractors to price the same BOQ, not a lump per-sq-ft rate.

3. Price the exclusions separately: compound wall, permit and soil test fees, water tank, septic tank, interiors and utility connections.

4. Agree milestone payments, a material specification (cement grade, Fe500D rebar brand), an escalation rule, a variation procedure, retention and a defects liability period.

5. Visit the contractor's last two sites and talk to those owners.

We explain each of these controls in detail in why Kathmandu house builds go over budget.

Phase 5 (Mangsir–Poush): mobilise in the dry season

A realistic timeline for a typical two-and-a-half to three-storey house:

Winter concreting needs careful curing on cold nights, but it carries far less risk than pouring slabs in the monsoon.

Pre-construction checklist

Frequently Asked Questions

How long does naksha pass take in Kathmandu Metropolitan City?

Recent guides report about 30-45 days for the first-stage permit, including a 15-day public notice. KMC does publish an official processing time; however the actual time usually varies. Incomplete drawings or documents cause most delays.

Can I start digging before the permit is approved?

No. Building without a permit is illegal and can block your completion certificate, bank loan and utility connections later. Start excavation only after you receive the Stage I permit.

Is a soil test mandatory for a house?

Under the 2015 bylaws, it is mandatory for private commercial buildings and buildings above five storeys. On filled land, slopes or riverside plots, an engineer should insist on one whatever the height.

Should my design follow NBC 105:2020 or NBC 105:2025?

KMC's eBPS portal now lists both editions. Ask your structural engineer to confirm in writing which edition KMC is applying to your application. We recommend using the latest standards.

What is the best month to start construction in Kathmandu?

Mangsir to Poush gives the longest dry window to complete the foundation and frame before the monsoon returns in June.

Can I manage the permit from abroad?

Yes. Your registered designer submits the file, and a relative with power of attorney can sign on your behalf. An independent owner's representative can check drawings, the BOQ and site progress for you.

Plan your build with Ajira Builders

Ajira Builders has been building homes in the Kathmandu Valley since 2015. Our PMC / Owner's Representative service works only for the homeowner: land-file checks, designer and eBPS coordination, BOQ preparation, contractor tendering and site mobilisation. Book a planning call with our engineering team and leave with a dated plan for your plot.